Contract No. 39-2024, endorsed on November 11, 2026, separates the Cristóbal terminal from the Petroport free zone and takes effect as of March 4, 2026.

Colonial facade of the Ministry of the Presidency with the national coat of arms and a scale model of fuel tanks and a ship in the foreground.
Illustrative image generated with AI.
By Redacción Nexo Capital · Mesa Editorial · November 20, 2026, 12:27

Official Gazette No. 30656-D of November 19, 2026 published Contract No. 39-2024 for the operation and administration of a fuel free zone, signed between the Ministry of the Presidency, through the National Energy Secretariat (SNE), and Puma Marine, S.A. The contract was signed on October 6, 2026 and endorsed by the Office of the Comptroller General on November 11, 2026.

Its first clause authorizes the company to operate a complex of tanks, pumping stations, piers, pipelines and a transshipment and storage terminal for crude oil, petroleum products, natural gas, biofuels and petrochemicals in the Cristóbal district of Colón. The second clause defines an area of about 7.99 hectares on two properties owned by the contractor, with port areas authorized by the Panama Maritime Authority (AMP) in 2018. The fifth clause records a certified investment of B/.50,982,910.46.

The thirty-sixth clause sets a twenty-five (25) year term, based on the amount invested. Until now Puma Marine operated with a user permit inside the free zone run by Petroport, S.A.; since the area ceased to be part of that concession on March 4, 2026, the new contract applies from that date. The sixth clause recognizes a special tax regime under Law 8 of 1987, and the nineteenth excludes price controls on exports and re-exports, although it allows them in the domestic market.

For the Atlantic marine fuel supply market, the contract consolidates an operator with its own free zone, which could widen its room to attract users and transshipments. In return, the company bears all commercial risk, cannot sell at retail and must maintain a performance bond of 10% of the investment, fire, civil liability and spill insurance policies, and allocate B/.508,354.74 to corporate social responsibility over the term, at B/.20,334.19 per year.

Before operating, the company must file with the SNE certifications from the fire department and on international technical and municipal standards, and it may not execute contracts with users without that agency's permit. The twenty-sixth clause allows the contract to be terminated if the company's concession with the AMP is cancelled. Nexo Capital will follow the start-up and permits of the new free zone.